Quick answer

Dump truck cycle time is the minutes for one full loop: queue and load, haul loaded, dump and ticket, return empty. Add them up, divide the working minutes in the day by the cycle and round down for loads per day. EXAMPLE: a 58-minute cycle in a 9-hour day is 9 loads; at 13.25 tons each, 119.25 tons.

Source: Arithmetic worked on this page; all inputs are EXAMPLES · checked 2026-10

Dump truck cycle time is the number that decides almost everything about a dump job: how many loads you run, how many trucks a contractor needs, and whether an hourly or per-ton offer pays better. I'm Steve Woods, a truck dispatcher at TruckSprint with 9 years in trucking. Here's how to calculate it, measure it, and use it to price work.

The four parts of a cycle

PartWhat's in itWhat stretches it
Queue and loadWaiting in line at the pit, loading, scaleTrucks ahead of you, slow loader, scale-house line
HaulLoaded run to the siteDistance, traffic, grades, loaded speed
Dump and ticketBacking in, dumping, getting the ticket signedTight sites, waiting for a spotter or the paver
ReturnEmpty run back to the pitDistance, traffic

Cycle time = queue and load + haul + dump and ticket + return.

Haul and return times come from distance and average speed, not posted speed. EXAMPLE: a 12-mile haul at an average 30 mph loaded takes 24 minutes; the same 12 miles back empty at 40 mph takes 18.

A worked example

EXAMPLE tri-axle loopMinutes
Queue and load10
Haul, 12 mi at 30 mph24
Dump and ticket6
Return, 12 mi at 40 mph18
Cycle58

Loads per day: a 9-hour day is 540 minutes; 540 / 58 = 9.3, so 9 complete loads. Round down: on per-ton work, a load that isn't finished by quitting time doesn't pay today.

Tons per day: 9 loads x 13.25 legal tons = 119.25 tons. The legal tons per load come from your axles and empty weight; see dump truck capacity.

How the cycle sets hourly vs per-ton pricing

The same day pays differently depending on the billing basis. Find the per-ton rate that matches an hourly offer:

Break-even per ton = hourly rate x hours / tons per day.

EXAMPLE: at $96.48 an hour (the EXAMPLE bid built in dump truck contracts), 9 hours pays $868.32. Spread over 119.25 tons, that's $7.28 a ton. A per-ton offer above $7.28 beats the hourly offer on this loop; below it, take the hourly.

Now add 7 minutes of waiting at the pit:

EXAMPLE58-minute cycle65-minute cycle
Loads in 540 minutes98
Tons119.25106
Per-ton rate matching $96.48/hour$7.28$8.19

Seven minutes of waiting cost a whole load, and the per-ton rate you'd need to break even jumps by 91 cents. That's why trucks on slow, congested jobs want hourly pay, and why per-ton offers deserve a hard look at the pit line. Public hourly rates for comparison are in dump truck hauling rates.

How many trucks a loader needs

Contractors and plants use the same numbers to size their truck count:

Trucks needed = cycle time / time to load one truck.

EXAMPLE: a 58-minute cycle and 6 minutes to load means 58 / 6 = 9.7, so about 10 trucks keep the loader working without long lines. Fewer and the loader sits; more and the extra trucks spend their day in the queue, which is your time and their money. When you're offered a job, ask how many trucks are on it.

Measure your real cycle

Plans are optimistic. Your tickets aren't. For a few days on a new job:

  1. Write the time out of the pit, the time on site and the time dumped on every ticket. Our haul ticket template has a column for each.
  2. Average each part, and note the longest wait.
  3. Use the average cycle for pricing and the worst cycle for your floor.

What usually stretches the cycle: a single loader for too many trucks, the scale-house line at shift change, a tight site with one way in, waiting on the paver or the foreman's signature, and afternoon traffic on the haul route.

Ways to shorten the cycle

  • Stagger start times with the other trucks so you don't all hit the pit at 7:00.
  • Know the site: ask for the dump spot and the way in before the first load.
  • Get tickets signed as you go, not in a stack at quitting time.
  • Carry more legal tons per trip where it fits the work: more axles or a transfer; see super 10 dump trucks.
  • Never shorten it by overloading or speeding. A fine or an out-of-service order costs more than any load.

TruckSprint no longer dispatches dump trucks. If you also run a 26 ft box truck, our desk can keep it loaded.

Sources

  • Arithmetic on this page; inputs labeled EXAMPLE
  • Legal payload method: 23 CFR 658.17 (Bridge Formula), see dump truck capacity

Questions carriers ask

What is dump truck cycle time?

The minutes it takes a truck to complete one full loop: wait and load at the pit, haul loaded to the site, dump and get the ticket signed, and drive back empty. Add the four parts and you have the cycle. It decides how many loads a truck can run in a day.

How do you calculate dump truck loads per day?

Divide the minutes in the working day by the cycle time and round down, because a half-finished load doesn't get paid on per-ton work. EXAMPLE: a 9-hour day is 540 minutes; at a 58-minute cycle that's 9 complete loads.

How many dump trucks does a loader need?

Divide the truck cycle time by the time it takes to load one truck. EXAMPLE: a 58-minute cycle and 6 minutes to load means about 9.7 trucks, so 10 keep the loader busy. Fewer and the loader waits; more and trucks queue at the pit.

Is hourly or per-ton pay better for a dump truck?

It depends on the cycle. Long waits and slow sites favor hourly pay; short, fast loops with quick loading favor per ton. Work out the per-ton rate that matches the hourly offer at your real cycle, then compare the two offers.

How do I measure my real cycle time?

Use your tickets. Write the time out of the pit, the time on site and the time dumped on every haul ticket for a few days. The averages give you load, haul, dump and return times for that job, including the waits nobody plans for.

Run your own loop in 30 seconds

Enter your load, haul, dump and return times. The calculator shows loads per day, tons, and what an hourly or per-ton offer pays.

Free, no signup.